Product Code Database
Example Keywords: bioshock -resident $28
   » » Wiki: Mindanao Railway
Tag Wiki 'Mindanao Railway'.
Tag

The Mindanao Railway, previously known as the Trans-Mindanao High Speed Railway, is a proposed railway system in , the southernmost major island of the . Originally proposed in 1936 as part of Manuel L. Quezon's efforts to strengthen the presence of Commonwealth government in Mindanao against the rising influence of Imperial Japan before World War II, the line was shelved. Other proposals and studies were made in the 1950s, 1990s, and the 2000s, but never materialized. The current line began development in 2018; however, construction has yet to start. It will be initially built as a single-track standard gauge system to be operated by , but will have provisions for upgrading to double-track and electrification through overhead lines.

The system will be constructed as a network long in its present form, totalling of track, with the centerpiece being a circumferential mainline that connects some of the major cities of the island. An east–west radial mainline will also be built to the Zamboanga Peninsula, and a number of other radial lines will serve as . As with other projects of the Philippine National Railways, the Mindanao Railway will be constructed in phases covering segments of various lengths.

The first phase, the segment of the circumferential mainline, will be the first section to be constructed. This segment was initially set to be partially opened by 2022, with the rest of its 17 segments being completed by the 2030s , but the entire project has been beset by delays with funding and construction. An official development assistance (ODA) loan from was planned for funding most of the project; however, the Philippine government backed out of pursuing it in 2023. While the project is still stalled, the government is starting again on the project in 2024. A fresh feasibility study was conducted by the Asian Development Bank (ADB). Another proposal is the third phase, or the Northern Mindanao Railway, a 54.8-kilometer high-capacity line connecting Cagayan de Oro, connecting the municipalities of and Villanueva, , which is under study from the Public-Private Partnership (PPP) Center.


History

Historical railways
The first attempt to construct a rail line in Mindanao was made in the 1890s, when the Spanish colonial government attempted to build a railway between and . However, this was never finished.

Not long after, a series of narrow-gauge railroads were opened by the American government in Mindanao. These short lines were constructed to transport supplies and United States Army personnel. A line was opened in Camp Keithley in what is now where trains carried war on . A gauge short line was also opened in , .

The best-documented system built by the government was the single-track line of the Davao Penal Colony in Davao del Norte. The prison was established in 1932 by the American government. It was converted into a facility for American POWs after its occupation by Imperial Japanese Army forces in 1942. Davao Penal Colony survivor Raymond C. Heimbuch wrote in his book that the line suffered from poor condition of the rolling stock and lack of maintenance of the tracks. There were 40 flatcars and a sole diesel locomotive, which replaced a steam locomotive whose tender survived after the war. The diesel locomotive would pair with 5 or 6 flatcars that carried prisoners, sacks of rice, or forestry products. The train took a 45-minute trip per way.

(2025). 9781436325240
According to an interview with POW survivor Hayes Bolitho in 2009, the line is estimated to be long. He also commented that prisoners were forced to push the train in case of rain or when ascending steep grades due to the poor conditions of the tracks. A few years after the war, a two-car train welcomed the party of then-president during his visit to the area.

At the same time, local plantations and lumber mills also built their own systems during the 1920s and the 1930s, typically serving freight trains from the production facilities to a port. At Port Lamon, Surigao del Norte, trains carried timber from the jungle and sawmill to the pier. One Class B was used by the Lumber and Development Company of Lanao del Norte during the 1920s and the 1930s. In , Lanao del Sur, a local company also ran freight trains through the town during the 1930s. In Misamis Oriental, the Anakan Lumber Company operated Heisler locomotives in the town of during the 1920s and 1930s.

These short lines were either destroyed during World War II or dismantled (the Davao Penal Colony line was dismantled due to its condition sometime after President Quirino's visit). The metal used was then sold to the due to the high market value of there. Despite closures of local freight railroads due to the rise of truck traffic, one line was established in the by the Tagum Agricultural Development Company (TADECO). It started operations in 1950 and had two diesel locomotives that hauled abacá and produce. The locomotives were decommissioned and stored in 2010.


Initial proposals
Proposals for the Mindanao Railway were published by the and The Far Eastern Review as early as August 1906. These proposed corridors include those surrounding , , , and . There were no proposed interconnections between these four lines due to the technology and rather low population density of the region during that time.

Then-president Manuel L. Quezon proposed the construction of an electrified railroad between Cagayan de Oro (then known as Misamis) and passing through the province of . It would have been electrified by overhead lines powered by the Maria Cristina Falls' hydroelectric power plant (now the Agus VI Hydroeletric Plant). This proposal was made in January 1936, and was taken note by Quezon's adviser Francis Burton Harrison. Some construction began the same year, but the project was left incomplete without a single track placed when construction was halted in 1940. (Also available at the University of Michigan, Ann Arbor, Michigan, USA).

After the war, Manila Railroad General Manager and later-Senator Prospero Sanidad proposed a standard-gauge railway in 1952 with consideration for a future electrified network. A network long was proposed for construction with the assistance of American firm De Leuw, Cather and Company.

The following lines were proposed, each at least long:

  1. , (100 km)
  2. Cagayan de Oro – Kibawe (140 km)—The route would have also passed by .
  3. – Kibawe (120 km)—A branch line would have passed by Parang, Maguindanao.
  4. , Agusan del Norte – , Agusan del Sur (120 km)—A branch line would have passed by .
  5. Butuan – (100 km)
  6. Davao City – Santa Josefa (110 km)
  7. – Kibawe (110 km)—A station would have also been built in the area of .
  8. Makar – , (150 km)—The area referred in this study as Makar is now divided between and T'Boli, South Cotabato.
  9. Davao City – Makar (110 km)
  10. – Santa Josefa (50 km)—A branch of Segment 4.

According to this older plan, Kibawe (then known as Kibawa) and Davao City were the main hubs for the network. Although never realized, it influenced the right-of-way of the present Mindanao Railway proposal, particularly on the circumferential main line.


Mindanao and the Philippine National Railway
When the Philippine National Railway (PNR) was created by virtue of Republic Act 4156 in 1964, establishment of a railway in Mindanao was made part of its mandate. Section 5 of the law explicitly stated that ₱50 million had been allocated for the survey and establishment of a railway on the island. When Republic Act 4156 was superseded by Republic Act 6366 in 1971, the same explicit mandate to create a Mindanao Railway, under the PNR, remained.

However, when the law enabling the PNR was amended by Presidential Decree 741 in July 1975, reference to a railway in Mindanao was omitted.


Return of the Mindanao Railway to the national agenda
On December 15, 1992, Fidel Ramos signed Memorandum Circular No. 23 which directed the formulation of the Medium-Term Philippine Development Plan 1993–1998. Section 4.4.2 of this plan focused on Transportation. Sub-paragraph "M" called for a feasibility study for the Mindanao Railway under a Build Operate Transfer (BOT) arrangement.


From the Mindanao Railway System Task Force to the Mindanao Railway Project Office
President Joseph Estrada created the Presidential Committee on Flagship Programs and Projects to identify projects for the administration. On October 7, 1998, the committee directed the Philippine National Railways, Public Estates Authority, and the Southern Philippine Development Authority to conduct preparatory studies for the Mindanao Railway System.

On June 28, 1999, Estrada signed Administrative Order 74, series of 1999 which allocated ₱10 million to the Mindanao Rail System Task Force to, as stated in the order, "act as the clearing house for policy and operational issues affecting the implementation of the MRS Project".

However, on February 11, 2002—after Estrada's impeachment the year before—President Gloria Macapagal Arroyo signed Executive Order 72, series 2002, which abolished the MRS Task Force. Later, however, Arroyo replaced the task force with another organization.

On May 25, 2006, President Gloria Macapagal Arroyo signed Executive Order 536 which created the Cebu Railway Project Office (CRPO) and the Mindanao Railway Project Office (MRPO) under the control of the Department of Transportation and Communication (DOTC). Both were charged formulating plans for, identifying funding mechanisms for, and developing railways in Metro Cebu and Mindanao, respectively.


Mindanao Strategic Railway Development Plan
The government made numerous studies and technical assessments during the 1990s. In the early 2000s, the Mindanao Strategic Railway Development Plan was formulated. The planned railway, with a total length of , was designed to span the entire island in a loop and was estimated to cost ₱66.5 billion. The plan for a railway divided into four phases: Laguindingan to Cagayan de Oro, Cagayan de Oro to Tagoloan, Laguindingan to , and Iligan to Linamon. The network would have linked urban centers across the island and was aimed to cut the 90-minute travel time by bus between Cagayan de Oro and Iligan to 15–20 minutes. The project was slated to start construction in 2011, and Saudi Arabia expressed interest in funding the project. The project was later discontinued.


2010s
As part of the updated 2011–2016 Philippine Development Plan, ₱400 million (US$8.85 million) was allotted for conducting feasibility studies to develop infrastructure projects such as railways and roads. In 2014, there were debates on whether the system would be privately managed or run by the Philippine National Railways, which intermittently operated inter-city rail services in at the time.

The Japan International Cooperation Agency (JICA) and the National Economic and Development Authority conducted studies for the construction of a rail system in the island of along with its partners starting in 2015. The proposal in 2015 resembled the 1952 right-of-way. The government planned to build the railway in six phases, with the first running from to . A pre-proposal conference was conducted in 2015, but the railway was not included in the Public-Private Partnership program.


Development

Phase 1
The railway in its present form began development in the late 2010s. While JICA was conducting initial studies, then-presidential candidate supported the construction of the railway. Upon Duterte's election, he aimed to begin construction of the first phase between the cities of and /ref> In 2018, the project, initially called the Trans-Mindanao High Speed Railway, was approved and received initial funding from Congress. The rest of the funding would have come from an official development assistance (ODA) loan from . However, construction was delayed after several issues, specifically after residents of a high-end near Davao City has requested the Department of Transportation (DOTr) to realign the railway line to avoid hitting an 18-hole .

The railway's route was modified into a system centered around a circular mainline. However, it was later reverted into the old right-of-way, but now incorporates the extensions and branch lines featured in the 2019 proposal. In its current state, the project has 18 segments to be divided into 10 phases.

On March 24, 2021, the DOTr Undersecretary for Project Implementation in Mindanao, Eymard Eje, Tagum mayor Allan Rellon, and Carmen mayor Virginia Perandos signed a deed of absolute sale for land to be used for the construction of the Tagumpay Train Village, a resettlement area for families affected by the project. As of April 2021, land acquisition from Panabo to Carmen was almost complete. On April 19, 2021, the city government of issued an ordinance prohibiting any unrelated construction on the right-of-way of the Mindanao Railway.

The Project Management Consultant Contract for the Tagum–Davao–Digos segment of the project was signed on October 20, 2021. It was also announced that the final length of the system would be .

In July 2022, the project funding was withdrawn after the Chinese government failed to act on the funding requests by the Duterte administration, including the Subic–Clark Railway (later Subic–Clark–Manila–Batangas Railway under a new initiative) and PNR South Long Haul projects. A month later, on August 11, Chinese Ambassador to the Philippines and Transport Secretary held formal talks ending in an agreement to restart negotiations for the three railway projects.

On September 30, 2022, the DOTr said that the project could be finished by 2028 if the loan for the project was finalized by 2023. However, such plans between the governments of the Philippines and China never progressed and materialized, and on October 25, 2023, the Philippine government announced that it officially withdrew its request for Chinese ODA funding.

After China withdrew from funding the project in 2024, the government decided to re-study the first phase of the project with the inclusion of freight services as part of its adjustments to the DOTr, and at the same time, the transportation department revamped the feasibility study of the project to use environmentally friendly or electric trains. At the same time, JICA announced that the funding decision for the project is not ready yet as it awaits the completion of a feasibility study with the revised project.

In July of that year, 3 foreign firms expressed interest interest in pursuing the project. Mindanao Development Authority Secretary Leo Tereso Magno said that there were 2 Korean and 1 Japanese firms their willingness to design and build the said project. In November, Vice President lamented the delay of the construction of the railway and made the pronouncement in a press conference in when asked that regarding the development, particularly its rumored cancellation. The pre-construction activities are still ongoing.

As of May 2025, there has yet to be any advancements, and DOTr Secretary stated: “Yes, these projects remain in the priority list of the President and in the priority list of the DOTr. However, it is difficult to say if we don’t have the funding yet. We cannot program a timeline for them,”. Nonetheless, the project is currently undergoing a revised feasibility study conducted by the ADB, via the Infrastructure Preparation and Innovation Facility. According to Dizon, "We will try our best to look for funds for the Mindanao Railway,".


Phase 3
The third phase of the project, also known as the Northern Mindanao Railway, started its development in 2022 and was approved by the NEDA board in March 2023. At the same time, PPP Center granted MRP Phase 3 P100 million in funding for its feasibility study via the agency’s Project Development and Monitoring Facility, a revolving fund that supports infrastructure projects. It became one of the 194 flagship infrastructure projects under the administration's Build Better More program. The planned project and a feasibility study conducted by India LLP are expected to be submitted in July 2024. The contract “will involve project preparation services for a preliminary assessment of the viability of MRP Phase 3 in Northern Mindanao,” the DOTr said in a statement. Among the aspects that will potentially be studied are the alignment of the railway, the number of stations, and the economic impact. It is a 54.8-kilometer railway line connecting Cagayan de Oro, connecting the municipalities of Laguindingan and Villanueva, Misamis Oriental. The Public-Private Partnership (PPP) Center is also backing the proposal.

Based on the project description, the railway project will include passenger railway stations, maintenance depots, operations control centers, connectivity to Languindingan Airport, connectivity to seaports, and transit-oriented developments (TOD). The railway will be designed to be capable of handling freight cargo at cargo terminals in the future.


Construction
The Philippines withdrew the proposed first rail system in Mindanao from Beijing's portfolio. Construction was deferred indefinitely. Prior to the withdrawal of the Chinese loan in 2023, the system was originally set to begin construction in the third quarter of 2021, with partial operations by 2022. The rest of the system will be opened between 2032 and 2037.

The start of construction was delayed in May 2022 as the DOTr did not receive the shortlist of the design-and-build contractors from the Chinese government.


Route
The Mindanao Railway is planned to be constructed in ten phases,, cites an AV presentation from the Department of Transportation (Philippines). with a total of of track to be built for the system. Phase 1 will be partially opened between and Carmen, Davao del Norte, by 2022, and full operations are expected by 2024.


Phase 1
Also known as the Tagum–Davao–Digos (TDD) segment, this phase involves the construction of a segment between the cities of and , passing through . It will have eight stations alongside two depots to be located in Tagum and Davao City, with the former being the segment's main yard. This is the only segment confirmed to have planned double-tracking and electrification upgrades in the future.
Carmen, Davao del Norte
Santa Cruz, Davao del Sur


Other proposed phases
  • Phase 2 – The second phase will involve a segment south of Phase 1 between the cities of and , passing through .

Hagonoy, Davao del Sur
,
General Santos City
Tupi, South Cotabato

  • Phase 3 – The third phase is estimated to be 54.8 kilometers long and connect the metropolitan area of Cagayan de Oro from Laguindingan to Villanueva. It was identified in the 2021 Master Plan for the Sustainable Urban Infrastructure Development in Metropolitan Cagayan de Oro and will be an important transportation mode as Cagayan de Oro develops as the fourth metro area, according to the National Spatial Strategy.

El Salvador City, Misamis Oriental
Cagayan de Oro
Tagoloan, Misamis Oriental
Villanueva, Misamis Oriental

  • Phase 4 – The fourth phase will involve a segment north of Phase 1 between the cities of Tagum and .

Trento, Agusan del Sur
Rosario, Agusan del Sur
San Francisco, Agusan del Sur

  • Phase 5 – Phases 4 and 5 are the last two projects in sealing the new circumferential mainline of the Mindanao Railway, which replaced the Cagayan de Oro–Pagadian–Digos segment.
    • Koronadal–Cagayan de Oro mainline segment and Davao City–Bukidnon branch (undetermined total length) – The Davao City–Bukidnon branch will meet with the other end of the main line of the Koronadal–Cagayan de Oro segment at , , according to DOTr. This right-of-way is different to the earlier proposals that would have passed by the area of Valencia and .
    • Butuan–Cagayan de Oro segment (170 km) – A branch line will be also constructed north from Butuan to Surigao City.
  • Phases 6–10 – These phases involve the construction of four radial lines, with one having an extension into the mainline network. will be the main hub of four of these segments and lines. The following branch lines are involved:
    • Cagayan de Oro– segment via (216 km)
    • Pagadian–Digos segment (242 km) – Digos is the southern terminus of Phase 1. This segment will also pass through Cotabato City and traverse the circumferential mainline via .
    • Pagadian– branch (122 km)
    • Pagadian– segment (222 km)
    • Butuan– branch (97 km)

The total length of the Koronadal–Cagayan de Oro and Davao City–Bukidnon segments, as well as future extensions on the line beyond Phase 10 such as the double-tracking of the Tagum–Digos segment, amounts to .


Design
The Mindanao Railway will be initially constructed as a single-track line with future upgrades to dual tracking and rail electrification. The right-of-way acquired for the alignment is sufficient for a dual-track system, thus facilitating the upgrade. Timothy John Batan, Department of Transportation Undersecretary for Railways, said he wanted these upgrades to be implemented at once. Like all proposed intercity lines of the Philippine National Railways, it will be built in . This is part of the larger efforts by the agency to convert its network from narrow to standard gauge, the first in Southeast Asia to do so.

The maximum speed of trains on the line is and the average speed is . Commuter trains will also have a headway of 13 minutes during partial operations for Phase 1. Lastly, the project suggests the use of the European Train Control System for its signalling and train control systems with at least Level 1 to be installed on the line.

A section of Phase 1 in shall also be connected to the Davao People Mover by a connecting bus service.


Electrification and double-tracking
The line will be initially constructed as a single-track line that will be by operated with diesel rolling stock, although upgrades to a standard electrified double-track mainline will be constructed in the future. The specific type of electrification system that will be adopted on the Mindanao Railway is yet to be determined. On the other hand, expansion of the single-track line to double-track has already been considered for at least the Tagum–Davao–Digos section, which is included in the total of track length of the entire system. For the current station arrangement however, shall be used to allow trains to stop without obstructing traffic from the opposite direction, especially with the target headway being 13 minutes.

If the electrification and double-tracking plans were adopted, the current maximum speed for the diesel line would be raised to , which is comparable to PNR's Luzon System's maximum speed and would count as higher-speed rail. The 2016 JICA study suggests the use of overhead catenaries on or before 2045.


High-speed rail
In 2018, the project was initially given the marketing title of "Trans-Mindanao High-Speed Railway". This was later simplified to "Mindanao Railway" after a maximum speed of was determined, which is less than half that of true . The name change also happened with the North–South Commuter Railway in and the Tel Aviv–Jerusalem railway in , both of which were marketed as "high-speed" to distinguish themselves from the much slower existing train services there.

Despite the change in the project title, there are plans for a genuine high-speed rail network in the region, and the proposed infrastructure of the Mindanao Railway was planned with future high-speed rail development in mind along as with all the proposed railways for PNR. The two shortlisted Chinese proponents also stated interest in designing a high-speed line that will be capable of running speeds of up to once the present project achieves successful operations.


Rolling stock

Under Chinese loan
In 2023, China backed out of providing loans to the Philippines for Mindanao Railway Project Phase 1. The system was supposed to accommodate both passenger and freight rolling stock, the latter due to its dual purpose to connect seaports around the island. Only the specifications for the commuter trains for the Tagum–Digos section was given as of December 2020. The design speed of the commuter trains is at , although speed will be limited to for passenger trains and for freight trains. The diesel multiple units that will be used in the commuter service are arranged in , and will be combined in the future for arrangement of four- and eight-car unit trainsets.

An earlier order also cited the purchase of rolling stock for the intercity section. This order includes 33 cars for the passenger service, which include six 5-car units and three spare cars for passenger trains, and 4 diesel-electric locomotives with 15 freight cars. The whereabouts of this order is yet to be determined.


Under revamped proposal for the first phase
In 2024, the government announced the proposed plan to change the system from a diesel-hauling to an electric one for the train sets. According to Transportation Secretary Bautista, he said that the diesel-powered trains were identified in the original study, but they will adopt a more modern and environment-friendly (eco-friendly) technology.


Notes

Page 1 of 1
1
Page 1 of 1
1

Account

Social:
Pages:  ..   .. 
Items:  .. 

Navigation

General: Atom Feed Atom Feed  .. 
Help:  ..   .. 
Category:  ..   .. 
Media:  ..   .. 
Posts:  ..   ..   .. 

Statistics

Page:  .. 
Summary:  .. 
1 Tags
10/10 Page Rank
5 Page Refs
1s Time